Title: GB-Edinburgh: Refurbishment of Fife Ness Lighthouse
Notice type: Competitive Contract Notice
Authority: Northern Lighthouse Board
Nature of contract: Not applicable
Procedure: Not applicable
Short Description: Fife Ness Lighthouse is at an elevation of 12m and a position of 56º 16.17’ N, 02º 35.10’ W. The character of the light is flashing white and red every 10 seconds with a range of white 21miles and red 20 miles. The lighthouse sits on a rock outcrop, which falls approximately 3m down to the shore to the south around the lightroom area. The station is bounded by a 2m concrete post and mesh fence topped with 3 layers of barbed wire. There is a tarmac track from the entrance gate up to the station entrance. The Lighthouse is a single storey building that consists of lantern room, control room and battery room. The light was first established in 1975. The proposed works principally involves the repair of and defective items and application of decorative / protective coatings to all external /internal surfaces of the structure. More specifically, the main items of project work are as listed below:- 1. Carry plant, tools and materials to site. 2. Ensure contractors own site welfare facilities accessible. 3. Carry out an Asbestos Refurbishment / Demolition Survey on the structure prior to the commencement of any work. The survey, sample collection and sample analysis must be carried by a UKAS accredited contractor in accordance with ISO 17020, ISO 17025 and Health & Safety Executive Guidance Notes; HSG 248, Asbestos: The analysts’ guide for sampling, analysis and clearance procedures” and HSG264, Asbestos: The survey guide. A copy of the report must be issued to the Engineer prior to work commencement. 4. All licensed removal work must be carried out by Asbestos Removal Contractors who are in possession of a current asbestos license issued by the Health and Safety Executive and who are members of the Asbestos Removal Contractors Association (ARCA). Asbestos Removal Contractors must be assessed in advance by the NLB QHSE department. 5. External work (Lighthouse Station) Wash down prepare and paint externally. Replace entire security fence. Remove obsolete emergency optic. Minor building refurbishment works. 6. Internal work (Lighthouse Station) Washdown, prepare and paint internals of lighthouse. Minor building refurbishment works. 7. Remove rubbish off site on a regular basis, photographs of welfare facilities to be provide to NLB at the start and end of each trip to ensure basic hygiene levels are met. 8. The Contractor must supply the NLB Project Leader with ‘as-built’ drawings and information for incorporation within NLB Operational and Maintenance documentation, which includes the Health and Safety file in line with current CDM Regulations. Programme The contractor must submit a works programme, at tender stage with a proposed start date for the sequence of works within this project. It is anticipated that the programme of scheduled works will start in July/August 2024 and take place over a period of 8 weeks. A mandatory site visit is scheduled for 24 July 2024. This is compulsory for all tenderers.
Published: 10/06/2024 10:55
Please note that the deadline for response to this opportunity has passed. However, you can still register or log-into the Delta eSourcing solution to prepare your Supplier Profile for future opportunities.

View Full Notice

Competitive Contract Notice

1. Title: GB-Edinburgh: Refurbishment of Fife Ness Lighthouse
2. Awarding Authority:
    Northern Lighthouse Board
    84 George Street, Edinburgh, EH2 3DA, United Kingdom
    Tel. 0131 473 3130, Email: procurement@nlb.org.uk, URL: https://www.nlb.org.uk/
    Contact: Graham Allan, Attn: Graham Allan
3. Contract Type: Works
      Sub Type: Execution

4. Description: Painting work of buildings. Fencing, railing and safety equipment installation work. Fife Ness Lighthouse is at an elevation of 12m and a position of 56º 16.17’ N, 02º 35.10’ W. The character of the light is flashing white and red every 10 seconds with a range of white 21miles and red 20 miles. The
lighthouse sits on a rock outcrop, which falls approximately 3m down to the shore to the south around the lightroom area. The station is bounded by a 2m concrete post and mesh fence topped with 3 layers of
barbed wire. There is a tarmac track from the entrance gate up to the station entrance. The Lighthouse is a single storey building that consists of lantern room, control room and battery room. The light was first established in 1975.
The proposed works principally involves the repair of and defective items and application of decorative / protective coatings to all external /internal surfaces of the structure.
More specifically, the main items of project work are as listed below:-
1. Carry plant, tools and materials to site.
2. Ensure contractors own site welfare facilities accessible.
3. Carry out an Asbestos Refurbishment / Demolition Survey on the structure prior to the commencement of any work. The survey, sample collection and sample analysis must be carried by a UKAS accredited contractor in accordance with ISO 17020, ISO 17025 and Health & Safety Executive Guidance Notes; HSG 248, Asbestos: The analysts’ guide for sampling, analysis and clearance procedures” and HSG264, Asbestos: The survey guide. A copy of the report must be issued to the Engineer prior to work commencement.
4. All licensed removal work must be carried out by Asbestos Removal Contractors who are in possession of a current asbestos license issued by the Health and Safety Executive and who are
members of the Asbestos Removal Contractors Association (ARCA). Asbestos Removal Contractors must be assessed in advance by the NLB QHSE department.
5. External work (Lighthouse Station)
Wash down prepare and paint externally.
Replace entire security fence.
Remove obsolete emergency optic.
Minor building refurbishment works.
6. Internal work (Lighthouse Station)
Washdown, prepare and paint internals of lighthouse.
Minor building refurbishment works.
7. Remove rubbish off site on a regular basis, photographs of welfare facilities to be provide to NLB at the start and end of each trip to ensure basic hygiene levels are met.
8. The Contractor must supply the NLB Project Leader with ‘as-built’ drawings and information for incorporation within NLB Operational and Maintenance documentation, which includes the Health
and Safety file in line with current CDM Regulations.
Programme
The contractor must submit a works programme, at tender stage with a proposed start date for the sequence of works within this project. It is anticipated that the programme of scheduled works will start in July/August
2024 and take place over a period of 8 weeks.
A mandatory site visit is scheduled for 24 July 2024. This is compulsory for all tenderers.
5. CPV Codes:
   45442110 - Painting work of buildings.
   45340000 - Fencing, railing and safety equipment installation work.

6. NUTS Codes :
   UKM - SCOTLAND

7. Main Site or Location of Works, Main Place of Delivery or Main Place of Performance: SCOTLAND,
8. Reference Attributed by the Awarding Authority: ENPR/LFIF/2323
9. Estimated Value of Requirement: Category I: 50K to 100K
Currency: GBP
10. Deadline for Expression of Interest: 22/07/2024 14:00:00
11. Address to which they must be sent:
    URL: www.delta-sourcing.com
   
12. Other Information:
Other Information: The contracting authority considers that this contract may be suitable for economic operators that are small or medium enterprises (SMEs). However, any selection of tenderers will be based solely on the criteria set out for the procurement.
For more information about this opportunity, please visit the Delta eSourcing portal at:
https://nlb.delta-esourcing.com/tenders/UK-GB-Edinburgh:-Refurbishment-of-Fife-Ness-Lighthouse/8S8YC59M92

To respond to this opportunity, please click here:
https://nlb.delta-esourcing.com/respond/8S8YC59M92
TKR-2024610-PRO-26524407
Suitable for VCO: Yes
Procedure Type:OPEN
Period of Work Start date: 31/07/2024
Period of Work End date: 30/09/2024
Is this a Framework Agreement?: no